Room Preparation, Structural & Extension

Our project managers work to the site plans provided by your designer. A standard build for a 12’x12’ room would run as follows:

Day 1 Site brief and materials short list. Rip out the old kitchen, tiles and flooring. Electrical inspection.
Day 2 Electrical inspection and 1st fix. Heating / plumbing inspection and 1st fix. Blockwork, structural, plastering, dry lining, floor levelling.
Day 3 Blockwork, structural, plastering, dry lining.
Day 4 Tiling, Preparation for decoration, Woodwork.
Day 5 Tiling, Decoration, 2nd Fix and Certification.

Structural alterations and extensions do of course take considerably longer though we still offer the same perspicacity through our involvement from the initial design, through planning and building.

Following completion of scheduled works we will commence the fitting of your kitchen. Normally you can expect this to take a full working week, after which a template will be taken for your granite work tops which will in turn be delivered and fitted within 7 to 10 days. It is during this time that any decorating works that you require will be carried out to complete your kitchen.